Future of the Leighton Buzzard Light Railway secured

c

Construction work has started on a major project that delivers a section of the Leighton Buzzard Eastern Link Road which forms part of a wider plan to provide homes, retail and community facilities, and a school in the eastern area of Leighton Buzzard. Funded by developer Arnold White Group, the work will ensure the future of the Leighton Buzzard Light Railway, resulting in the track being diverted a short distance away from its original route alongside Vandyke Road in order for it to run under a bridge carrying the new link road.

The project which is already well underway is being facilitated by Fox (Owmby) Limited as the main contractor supported by railway contractor Alan Keef Ltd and is due for completion later this year.

Leighton Buzzard Railway General Manager Joe Horsley said: “The railway would like to place on record its thanks to all parties involved, including Arnold White Group, Fox (Owmby) Limited, Alan Keef Ltd, Stuart Michael Associates, Central Bedfordshire Council and The Railway Inspectorate, for working together with us to ensure the survival of the town’s major tourist attraction. This is an elegant and practical solution to a potentially awkward crossing of road and rail, and we look forward to our customers enjoying the results of this partnership next year.’

James Gudgin, Contracts Director at Fox (Owmby) mentioned: “The diversion includes a 45m long rail underpass, built using 46 precast concrete arch sections and is constructed offline. This allows us to build the diverted section of track, and the bridge without impacting on the railway operations. Once connected in, works to build the link road over the current railway alignment will be completed.”

Kate Groves of developer Arnold White Group: “As part of our works at Chamberlains Barn, it was clear that we needed to create an innovative solution which delivers the Leighton Buzzard Eastern Link Road while also keeping the Leighton Buzzard Railway running. We are delighted to help to secure the future of Leighton Buzzard Railway and ensure that this significant local tourist attraction can be enjoyed for many years to come.”

The project team has already provided an upgraded access crossing allowing contractors to cross the line during the construction period ensuring the safety of both site workers and passengers on the railway. The construction will continue throughout the summer months with the new track due to be connected in November once the railway has completed its main operating season.

Tony Tomkins

Avatar


Latest News from FEDECRAIL

IMG_1591
Update 61
Published: 21st April 2024

Important Updates from Fedecrail / Wichtige Updates von Fedecrail / Mises à jour importantes de Fedecrail Dear Members / Liebe Mitglieder / Chers membres, We …

Read More
IMG_1506
Online attendence for fedecrail conference 2024
Published: 12th April 2024

Join us for the highly anticipated Fedecrails Conference on May 3rd and 4th, where the world of heritage railways and tramways converges online! We’re thrilled …

Read More
IMG_1411
Update 60
Published: 1st March 2024

Dear Members, We’re thrilled to announce that Update 60 is now landing in your inbox, packed with the latest developments and insights into our operations! …

Read More

Ukraine